Project roof area: 20,000 square meters(take this scale as an example)
Project construction scale: 1.2MW
Total investment: 120 million yuan
Annual electricity production:1.2 million degrees
The total electricity production:30 million degrees
Construction period: 3 months
Construction period: 1 month
Operating cycle: 25 years
Emission reduction targets: annual savings of 576 tons of standard coal,
1595 tons of carbon dioxide, 48 tons of SO22.

What kind of roof can be built power station?

 Various types of industrial and commercial buildings' roofs, roofs of public buildings;
Steel roof, frame roof, T-type roof and other roofing;
Flexible area requirement, 5000 square meters above;
Good sunshine, occlusion as little as possible;
Roof owners' electricity consumption is large.

What are the benefits of building a power station?

Cheap electricity purchase, lower your electricity bill;
Reduce the energy consumption of the owners: the roof is effectively covered,
Summer indoor temperature can be reduced by an average of 2-3℃;
Enhance corporate image, complete enterprise energy-saving and emission reduction targets;  
Alleviate summer power cut;
Extend the roof life;

A wholly owned by buildingA wholly owned by building

Customers pay no money;
Versol will pay all money;
and provide EPC and maintenance.
Customers enjoy preferential electrovalence

Funded by bothFunded by both

Customers and Versol invest together to development;
Versol provides EPC and
maintenance.
Customers enjoy a stable income in accordance with the proportion.

Versol pays all money, what's your income?

Roof owners' enterprise enjoy preferential electrovalence.(88%)

Take the example of 100,000 square meters roof(Hangzhou):

The annual electricity production of the project is 8 million kWh, and the annual electricity consumption of the enterprise is 870 thousand Yuan.  
8 million degrees * 0.906 yuan / kWh (large industrial peak electricity price) * 0.12 = 870,000 yuan

Develop power station together
7-10 years recovery costs, sit and enjoy the benefits of 25 years

Take the example of 100,000 square meters roof(Hangzhou):

The annual electricity production of the project is 8 million kWh,
If all put grid, your annual income: 1.2353 (on-grid tariff + subsidy) * 8 million degrees / 80 million (total investment) = 12.3%.
If each half, Your annual income: (50% * 8 million degrees * 0.906 + 50% * 0.4153 * 800 million degrees +800 million degrees * 0.82) / 80 million = (362.4 +332.24 +656) million / 80 million = 16.88%.
If you own all, your annual income: (800 million degrees * 0.906 + 800 million degrees * 0.82) / 80 million = (724.9 +656) million / 80 million = 17.26%.

Nation subsidy policy

Distributed:The subsidy standard for electricity price is 0.42 yuan per kilowatt-hour (including tax, the same below),Since the PV power project has been put into operation, it will carry out the benchmarking grid electricity price or the subsidy standard for electricity price, the term is 20 years in principle. Photovoltaic power determines the 2016 benchmark price, the price after 2017 will be formulated separately.

Centralized:Ningxia, Qinghai Hercynian, Jiayuguan, Wuwei, Zhangye, JIuquan, Dunhuang, Jinchang in Gansu, Hami, Tacheng, Altay, Karamay in Xinjiang, Chifeng, Tongliao, Xing'an League, Hulunbeier in Inner Mongolia, 0.8yuan/kwh
Beijing, Tianjin, Heilongjiang, Jilin, Liaoning, Sichuan, Yunnan, Chifeng, Tongliao, Xing'anmeng, Hulunbeier in Inner Mongolia, Chengde, Zhangjiakou, Tangshan, Qinhuangdao in Hebei, Datong, Shuozhou, Xinzhou in Shanxi, Yulin, Yan'an and Qinghai in Shanxi, Gansu, Xinjiang excpet Hami, Tacheng, Altay, Karamay 0.88yuan/kwh Other places:0.98yuan/kwh

The policy of different provinces and cities


Note:Subsidy is different in different cities and counties, for example in Yuhang:0.42+0.1+0.4153+0.1+0.2=1.2353yuan/degree

Why do you choose Versol?

Because we have the most reliable team, we are the best teammates.

Strategic alliances

Versol

Responsible for the development and design

As the world's mainstream market suppliers with leading technology, Versol is responsible for the design and development of distributed power stations to ensure that the power station is in line with the world leading level.

Chint

Responsible for the EPC construction of the project

Zhejiang CHINT New Energy Development Co., Ltd. is mainly engaged in the field of photovoltaic power station investment, construction, operation and foreign turnkey business, is the largest private photovoltaic power production enterprise, the cumulative investment has built more than 1200 MW photovoltaic power station.

Guokai New Energy

Responsible for holding power station

Guokai New Energy Technology Co.,Ltd registered with capital of 12 billion, was invested in 50 billion, is the enterprise directly under the National Development Bank, is the owner of a distributed power station, to provide strong financial support for the power station. It is guaranteed that national country is in charge of power station.

How to build power plants?How to build power plants?

Management process

Management process

Time:3 months